💼 Jobs & benefitsFeedbackIn progress
Huime community · 6 Sept 2026
Women want roles in restoration work and livelihood opportunities
MAIS Eco · 25 Nov 2026
Women will be included in project work and livelihood support. Selection will be fair and open, with clear pay, and women's groups will be consulted on livelihood activities.
✓ What changed in the project
Written into our commitments: women are included in project work and livelihood support, selection is fair and open with clear pay, and women's groups are consulted on livelihood activities.
Raised 6 Sept 2026Answered 25 Nov 2026
💼 Jobs & benefitsFeedbackIn progress
Huime community · 6 Sept 2026
Women want organised women's groups to take part in the project
MAIS Eco · 25 Nov 2026
Thank you. We will discuss forming women's groups at separate women's sessions in each area, including how they can take part in nursery, planting and monitoring work.
✓ What changed in the project
Women's sessions are planned in each priority area to discuss forming women's groups and their part in nursery, planting and monitoring work.
Raised 6 Sept 2026Answered 25 Nov 2026
🤝 Engagement & consentFeedbackIn progress
Huime community · 6 Sept 2026
Keep consulting chiefs, landlords, women and community members inclusively
MAIS Eco · 25 Nov 2026
Agreed. Besides meetings with chiefs and landlords, we will hold separate sessions for women and young people, and meetings with fishers and other resource users, in each area.
✓ What changed in the project
Added to our plan for each priority area: separate sessions for women and for young people, and meetings with fishers and other resource users.
Raised 6 Sept 2026Answered 25 Nov 2026
🤝 Engagement & consentFeedbackResolved
Huime community · 6 Sept 2026
Chief asks the team to formally meet his paramount chief next
MAIS Eco · 25 Nov 2026
Done: the team met the paramount chief, Torgbui Afla Awunor Detu IX, and sub-chiefs on 24 September 2026.
✓ What changed in the project
We met the paramount chief, Torgbui Afla Awunor Detu IX, and his sub-chiefs on 24 September 2026.
Raised 6 Sept 2026Answered 25 Nov 2026
🗺️ Land & rightsFeedbackResolved
Klikor community · 30 Aug 2026
Wetland permission rests with the chiefs; individuals cannot override it
MAIS Eco · 25 Nov 2026
Agreed. We will only work on land with the consent of its customary landholders, given through their own decision-making with the chiefs and elders, and will not deal with individuals against that decision.
✓ What changed in the project
Consent is sought only from the customary landholders through their own decision-making with their chiefs and elders; the draft land agreements are written that way, and we do not sign with individuals against that decision.
Raised 30 Aug 2026Answered 25 Nov 2026
💼 Jobs & benefitsFeedbackIn progress
Klikor community · 30 Aug 2026
Project should be owned at Electoral Area level, not as a private project
MAIS Eco · 25 Nov 2026
Agreed in principle. Land stays with its owners, and the draft benefit-sharing model proposes that 20% of carbon credit revenue goes to a Community Investment Fund run with community representatives. How it works in each area will be agreed with the community.
✓ What changed in the project
Shaped the benefit-sharing proposal: 20% of credit revenue goes to a Community Investment Fund, with a committee in each area whose members are mostly elected by the community (Draft Benefit-Sharing Model v0.1; Community Project Guide v1.2).
Raised 30 Aug 2026Answered 25 Nov 2026
🤝 Engagement & consentFeedbackIn progress
Klikor community · 30 Aug 2026
Traditional prayers with chiefs and priests must precede project activities
MAIS Eco · 25 Nov 2026
Agreed. We will ask the chiefs to arrange the customary rites before any project activity begins.
✓ What changed in the project
Customary rites are arranged with the chiefs before project activity in an area; one was held with landowners in June 2026.
Raised 30 Aug 2026Answered 25 Nov 2026
🤝 Engagement & consentFeedbackIn progress
Gbugbla community · 28 Aug 2026
Meet the Dumegawo and elders of Apeyime and Torwe before the main community meeting
MAIS Eco · 25 Nov 2026
Agreed. The team will meet the family heads and elders of Apeyime and Torwe before the main community meeting.
Raised 28 Aug 2026Answered 25 Nov 2026
🤝 Engagement & consentFeedbackResolved
Aflao community · 8 Aug 2026
Give communities and Assembly Members advance notice of future meetings
MAIS Eco · 25 Nov 2026
Agreed. We now give at least two weeks' notice of meetings through Assembly Members and Unit Committees where possible, and information materials 7 to 30 days before any meeting where decisions are discussed.
✓ What changed in the project
We now give at least two weeks' notice of meetings through Assembly Members and Unit Committees, and hand out information 7 to 30 days before any meeting where decisions are discussed (recorded in the booklet distribution register).
Raised 8 Aug 2026Answered 25 Nov 2026
🤝 Engagement & consentFeedbackResolved
Aflao community · 2 Aug 2026
Return to meet family heads (Dumegawo) and landlords before going further
MAIS Eco · 25 Nov 2026
Done: the team returned on 9 August 2026 and met the landlords, family heads and sub-chiefs of the six electoral areas.
✓ What changed in the project
We went back on 9 August 2026 and met the landlords, family heads and sub-chiefs of the six electoral areas before going any further.
Raised 2 Aug 2026Answered 25 Nov 2026
🏛️ Permits & governmentFeedbackIn progress
Anloga community · 19 Jun 2026
Run background checks on consultants and collaborators
MAIS Eco · 25 Nov 2026
We engage consultants and partners only under written agreements, and will check the registration and references of anyone working with communities.
✓ What changed in the project
Consultants and partners now work with communities only under written agreements, and we check their registration and references first.
Raised 19 Jun 2026Answered 25 Nov 2026
🏛️ Permits & governmentFeedbackIn progress
Anloga community · 19 Jun 2026
Provide regular progress reports and documentation to the Assembly
MAIS Eco · 25 Nov 2026
Agreed. We will send the Assembly a progress report every quarter with copies of key documents.
✓ What changed in the project
Added to our commitments to the Assembly: a progress report every quarter, with copies of key documents.
Raised 19 Jun 2026Answered 25 Nov 2026
🏛️ Permits & governmentFeedbackIn progress
Anloga community · 19 Jun 2026
Submit a feasibility report to the Assembly by 1 July
MAIS Eco · 19 Jun 2026
Project lead committed to submit a feasibility report on or before 1 July.
Raised 19 Jun 2026Answered 19 Jun 2026
🏛️ Permits & governmentFeedbackIn progress
Anloga community · 19 Jun 2026
Suspend drone flights until all documents and permits are verified
MAIS Eco · 19 Jun 2026
Project lead agreed to suspend drone flights and field operations until permits are approved.
Raised 19 Jun 2026Answered 19 Jun 2026
🌿 Mangroves & environmentConcernIn progress
Anloga community · 19 Jun 2026
Planting is restricted within about 100 m of water bodies in the Ramsar site
MAIS Eco · 25 Nov 2026
Noted. Planting sites will follow the Ramsar site rules and the Forestry Commission's conditions, and will be checked with the Commission before any planting.
✓ What changed in the project
Added to how we choose planting sites: areas the Ramsar rules restrict near water bodies are left out, and each site is checked with the Forestry Commission before planting.
Raised 19 Jun 2026Answered 25 Nov 2026
🏛️ Permits & governmentFeedbackResolved
Anloga community · 19 Jun 2026
Map all NGOs' mandates in the district to avoid duplication
MAIS Eco · 25 Nov 2026
We have mapped the organisations and projects working on mangroves in the area, and coordinate with them to avoid duplication. We are glad to contribute to the Assembly's own map.
✓ What changed in the project
We mapped the other mangrove projects in the area and now work with the Adaptation Fund project at Keta (UN-Habitat and ActionAid Ghana) so that our work does not overlap.
Raised 19 Jun 2026Answered 25 Nov 2026
🏛️ Permits & governmentConcernResolved
Anloga community · 19 Jun 2026
Field staff need written authorisation; no community contact without district knowledge
MAIS Eco · 25 Nov 2026
Field staff carry written authorisation and copies of our permits, and we inform the District Assembly before community visits.
✓ What changed in the project
Field staff now carry written authorisation and copies of our permits, and we tell the District Assembly before community visits.
Raised 19 Jun 2026Answered 25 Nov 2026
🏛️ Permits & governmentFeedbackIn progress
Anloga community · 19 Jun 2026
Share presidential approval and Forestry Commission letters with the Assembly
MAIS Eco · 19 Jun 2026
Project lead agreed to send soft copies of all approvals and permits for the Assembly's files.
Raised 19 Jun 2026Answered 19 Jun 2026
🏛️ Permits & governmentFeedbackIn progress
Anloga community · 19 Jun 2026
Submit registration certificate, constitution and permits to the Assembly for approval
MAIS Eco · 19 Jun 2026
Project lead agreed to submit all registration documents and permits to the Assembly by Monday.
Raised 19 Jun 2026Answered 19 Jun 2026
🤝 Engagement & consentConcernIn progress
Anloga community · 19 Jun 2026
Poor communication is fuelling rumours about NGO intentions and land use
MAIS Eco · 25 Nov 2026
We are improving how we communicate: plain-language booklets in English and Ewe, this public register, a grievance contact and online form, and information meetings in each community before any decision. The project does not buy or take land; land stays with its owners.
✓ What changed in the project
Made in response: plain-language booklets in English and Ewe that say the land stays with its owners, this public register, the documents page on our website, and a grievance contact and online form in both languages.
Raised 19 Jun 2026Answered 25 Nov 2026
🤝 Engagement & consentConcernResolved
Anloga community · 19 Jun 2026
Local leaders left out until the survey stage, causing distrust
MAIS Eco · 25 Nov 2026
We accept this: local leaders should have been engaged earlier. Leaders are now met first in each area, and no community will be asked for a decision until it has the information and time it needs, through a process it agrees.
✓ What changed in the project
Leaders are now met first in each area, and no community is asked to decide anything until it has agreed its own consent process (FPIC protocol) and had the information and time it needs.
Raised 19 Jun 2026Answered 25 Nov 2026
🤝 Engagement & consentFeedbackResolved
Anloga community · 19 Jun 2026
Assembly and chiefs must be engaged before any community activity starts
MAIS Eco · 25 Nov 2026
Agreed. We now brief the District Assembly, chiefs and Assembly Members before working in any community, and our engagement plan requires it. For example, the Assembly Members arranged the August focus groups.
✓ What changed in the project
Changed the order of our work: the District Assembly, chiefs and Assembly Members are briefed before any activity in a community. Since June 2026 this is how every area has been approached; the Assembly Members arranged the August focus groups.
Raised 19 Jun 2026Answered 25 Nov 2026
🌿 Mangroves & environmentQuestionResolved
Abolove community · 23 Jan 2026
Our water is salty, will the mangroves survive?
MAIS Eco · 26 Jan 2026
We explained that it depends on species selection, and appropriate groundworks to manage hydrology
Raised 23 Jan 2026Answered 26 Jan 2026
🌿 Mangroves & environmentQuestionResolved
Abolove community · 23 Jan 2026
Will there be one or more than one nursery?
MAIS Eco · 26 Jan 2026
Depends on the land survey, may end up having one central nursery, but not yet decided
Raised 23 Jan 2026Answered 26 Jan 2026
💼 Jobs & benefitsQuestionResolved
Abolove community · 23 Jan 2026
How and when does the community benefit from carbon credits?
MAIS Eco · 26 Jan 2026
Initially employment from the up-front investment. Exact starting point unknown - depends on the tree growth - but years 5-8 we will have paid the investor back and money can begin to flow into the community investment fund. The investment fund sits MAIS and the community and we collectively decide on how best to invest the funds
✓ What changed in the project
The booklets now say plainly when money can reach communities: jobs first, then 20% of every credit sale into the Community Investment Fund, with estimates and ranges (Booklet v1.1, Guide v1.2, November 2026).
Raised 23 Jan 2026Answered 26 Jan 2026
💼 Jobs & benefitsQuestionResolved
Abolove community · 23 Jan 2026
Will there be skills training and coaching programs
MAIS Eco · 26 Jan 2026
YES INDEED!
Raised 23 Jan 2026Answered 26 Jan 2026
ℹ️ About the projectQuestionResolved
Abolove community · 23 Jan 2026
What countries do MAISECO come from?
MAIS Eco · 26 Jan 2026
Many countries. On our team we have people from the United Kingdom, India, Ghana, Benin, and Ireland
Raised 23 Jan 2026Answered 26 Jan 2026
💼 Jobs & benefitsQuestionResolved
Abolove community · 23 Jan 2026
Will there be employment opportunities for youth?
MAIS Eco · 26 Jan 2026
Absolutely, and in the long-term we hope to build sustainable livelihoods and businesses for the communities
✓ What changed in the project
Local people, young people included, get priority for project jobs (Community Project Guide v1.2), and youth-only sessions are planned in each priority area.
Raised 23 Jan 2026Answered 26 Jan 2026
🏛️ Permits & governmentQuestionResolved
Abolove community · 23 Jan 2026
Are you working with Forestry
MAIS Eco · 26 Jan 2026
Yes, we are working with all government entities that we are required to work with and more: the presidential special initiative, the CMO, the EPA, and the Forestry
Raised 23 Jan 2026Answered 26 Jan 2026
ℹ️ About the projectQuestionResolved
Abolove community · 23 Jan 2026
When can we start!
MAIS Eco · 26 Jan 2026
Yes, we are working with all government entities that we are required to work with and more: the presidential special initiative, the CMO, the EPA, and the Forestry
Raised 23 Jan 2026Answered 26 Jan 2026
🗺️ Land & rightsQuestionResolved
Abolove community · 23 Jan 2026
Do we have to stop cutting down mangroves now?
MAIS Eco · 26 Jan 2026
Not right away, but gradually as we provide alternatives yes
✓ What changed in the project
Written into our plans: no limit on cutting starts until an agreed replacement, such as other fuel or woodlots, is in place (Community Project Guide v1.2 and the draft agreements).
Raised 23 Jan 2026Answered 26 Jan 2026
🌿 Mangroves & environmentQuestionResolved
Abolove community · 23 Jan 2026
What about existing trees and prevention credits
MAIS Eco · 26 Jan 2026
We are exploring the possibility of prevention credits - it’s a different process but yes we would like to do so
Raised 23 Jan 2026Answered 26 Jan 2026
💼 Jobs & benefitsQuestionIn progress
Abolove community · 23 Jan 2026
How many people will be employed to plant
We are looking into this.
Raised 23 Jan 2026Answered 26 Jan 2026